LV and HVA Tests on Load Banks
LV and HVA tests on load banks to test 6 new generators of 2 MVA
Context
Project Type :
Temporary Energy
Location :
Saint Denis (93)

Problem
- Working on a Paris-based data center operated by one of the largest administration companies in the world.
- Installation of 6 new generators of 2 MVA
- The customer requested that we conduct various tests:
- Low voltage tests of new generators installed
- Load distribution tests between the generators on the 20 kV circuit
Solution
Phase 1: LV Tests
- Load banks, both resistive and inductive of 3 MVA
- 900 m of cables HO7RNF – 500²
- 2 days of tests
Phase 2: HVA Tests
- Load banks, both resistive and inductive of 3 MVA
- Multi-voltage transformers 3150 kVA
- 900 m of cables HO7RNF – 500²
- 100 m of HVA cables
- 2 days of tests